Pool removal cost in St. Louis

Filling in an inground pool in the St. Louis area costs about $3,000–$9,000. Removing it completely, so the yard is buildable again, costs about $5,000–$16,000. Concrete pools, tight access and long hauls push the price up. Local cities and counties require a demolition permit first.

Partial removal (fill in)
$3,000–$9,000, 2–5 days
Full removal
$5,000–$16,000, 5–7 days
Permit
Demolition permit, $10–$200 in the cities we checked
Before digging
Call 811 at least 2 working days ahead

Partial removal vs. full removal

Partial removal drains the pool, punches drainage holes through the floor, breaks off the top of the walls and fills the hole. The rest of the shell stays buried. It is the cheaper option and the one most homeowners are first quoted.

Full removal breaks out and hauls away the whole shell, then fills the hole in compacted layers. It costs more, but the ground can carry a patio, addition or garage later, and there is nothing buried to explain to a buyer.

ComparePartial removalFull removal
Typical St. Louis cost$3,000–$9,000$5,000–$16,000
What stays in the groundThe pool floor and lower walls, broken upNothing
Building on the spot laterLawn or garden only, unless an engineer signs offPossible with documented compaction
Time on site2–5 days5–7 days
Best forA concrete pool you will turn into lawnVinyl and fiberglass pools, resale, any future building

Vinyl-liner and fiberglass pools are usually removed completely. A liner, steel or polymer walls and a fiberglass shell do not break down into fill the way concrete does. That is why the cost gap between pool types is smaller than you might expect: Fixr puts vinyl at $3,000–$10,000, fiberglass at $5,000–$10,000 and concrete at $3,000–$15,000.

What published pool removal prices say

No two cost guides agree, mostly because they mix partial and full jobs. Here is every figure we checked and when it was published.

SourcePartialFullNotes
Fixr (national, updated January 2025)$3,000–$7,000$5,000–$15,000Full-removal average $7,500; permits $50–$250
Bob Vila (national, March 2023)$4,500–$6,250$4,000–$16,000Full-removal average $9,000; about $500 for an engineer
Angi (St. Louis page, undated)$2,380–$9,510$3,805–$15,215Average $5,706; we could only read a summary of this page

Our planning ranges sit across those figures. St. Louis labor runs a little below national averages, but haul distances, rock and clay soil, and the permit steps below land on top.

What moves the price

Inground pool shell under construction with formwork in place
Stock photography for illustration. Removal is construction in reverse: the same access, excavation and soil questions that set a new pool's price set the cost of taking one out.

Pool removal permits in the St. Louis area

Removing a pool is demolition, and local cities treat it that way. Most require utility disconnection letters and a locate ticket before they issue the permit, and an inspection before the hole is closed.

WherePermitRules worth knowing
Creve Coeur$200 plus a $2,000 refundable escrowThe form has a swimming pool box. Needs a St. Louis County waste disposal authorization, an asbestos report or permit, a 48-inch safety fence and erosion control. Finish within 30 days. Backfill must be clean dirt or rock, never wood or construction debris.
Unincorporated St. Louis CountyDemolition permit; call to confirm the feeThe county requires a permit to demolish any structure, and its health department issues a separate demolition release. We could not confirm from the county's own pages how it treats a pool. Call the county permit office before you hire anyone.
City of St. LouisPulled by a city-certified demolition contractorValid for 30 days. Clean fill only, no pieces over 12 inches, no wood, metal or construction debris. The top 12 inches must be topsoil, seeded and strawed.
St. Charles County$160 for an accessory structureIncludes a $100 environmental fee. Rubble can stay in the hole only with approval, compacted and under 24 inches of clean fill. The site must be graded and seeded before the final inspection.
City of St. Charles$100 plus a $500 refundable depositUtility letters required. The permit expires after 3 months.
WentzvilleDemolition applicationConstruction and demolition waste cannot be buried on site.
Edwardsville, IL$10 for an accessory structureAny demolition work needs a permit.

Checked against city and county sources in October 2026. Fees change; confirm with the office before work starts. Other cities follow the same pattern. For who handles permits where you live, see pool permits by city.

Call 811 before anyone digs

Missouri law requires notice at least 2 and no more than 10 working days before excavation. In Illinois, JULIE needs at least 2 working days' notice. Your contractor normally places the ticket, but ask for the number; several cities want it on the permit application.

Selling a house with a filled-in pool

The Missouri REALTORS seller's disclosure form we reviewed asks whether you know of any fill on the property. A filled-in pool is fill. We are not lawyers and this is not legal advice, but the practical answer is the same either way: keep the permit, the final inspection and any compaction report together, so the buyer's inspector and lender have the paperwork instead of a question.

If you think you might ever build where the pool was, choose full removal with documented compaction. Putting a footing over a partly removed pool is the scenario everyone in this business warns about.

Questions to ask a removal contractor

Removing a pool to build a new one?

If the old pool is failing and you want a new one, a builder can often reuse part of the excavation, and the removal becomes one line of a single contract. New inground pools in St. Louis currently run $45,000 to $150,000+; the pool cost guide breaks that down.

Replacing an old pool?

Get matched with a local builder who can price the removal and the new pool together.

Get matched with a local pool builder See pool permits by city

Sources

Published October 27, 2026. Planning ranges, not quotes.